Ardsley Bridge Modifications Works

The client

Akona was contracted under NEC3 to deliver a comprehensive package of OLE and lineside civils work to facilitate the essential bridge repair works associated with the M62 overbridge crossing the East Coast Mainline. Our scope of work encompassed the full range of OLE and civils work, including ECI/ design development, CRE construction, procurement of materials, provision of plant, labour and associated Network Rail hand back.

Our task was to provide the OLE enabling works for the project anchoring the Return Conductor wire on either side of the bridge to enable the civils bridge repair works to be carried out. Our team managed the full OLE and ancillary civils tasks, including bridge drilling, proof/pull testing, SPS installation, anchoring of the return conductor, and the associated bonding. Additionally, we executed lineside troughing works to accommodate the diversionary route for the return conductor. To complete the works Akona Concepts engaged Story Plant to provide the RRV plant and POS services for the project.

The successful delivery of this project underscores our capability to manage complex rail infrastructure tasks with precision and efficiency. We are proud of our team’s performance and their contribution to the overall success of the Ardsley Bridge Project.

The task

 

 

 

 

 

The OLE return conductor wire was causing electrical safety issues and preventing essential civils repair work on the bridge to be carried out.

The solution

 

 

 

 

 

Akona were tasked to anchor the return conductor wire to the face of the bridge and provide a diversionary route to enable essential civils bridge repair works to take place.

The result

 

 

 

 

 

All works completed safely and successfully for the client meeting the strict programme timelines of the project.

Summary

 

 

 

 

 

This project showcased our capability to deliver minor OLE works efficiently and competitively.

“Akona provided ECI which enabled a robust programme and design to be developed to meet tight construction deadlines required for the project. Akona executed all stages of planning, preparation and delivery on time and were professional throughout. We wouldn’t hesitate to recommend Akona to anyone and consider Akona an industry leader in their field of expertise.” Contracts Manager, Balvac Balfour Beatty

Similar projects

Ardsley Bridge

+

Innovation is key to Akona approach we are therefore proud to work alongside media specialists, who have a track-record of achievement in the rail industry…

Read more

Great Western Electrification

+

Akona Concepts were tasked to support the engineering and design project teams with suitable junior and assistant engineers…

Read more

St Helens and Huyton to Roby

+

Akona Concepts were instrumental in the delivery of both projects, providing engineering assurance, project management and construction delivery…

Read more

Liverpool Lime Street Remodelling

+

We provided multiple OLE construction management and delivery teams to support both projects that were running concurrently…

Read more

Want to learn more about how we may help?

Contact us